Definitions for "Late Finish Date"
Keywords:  milestone, delay, critical, lfd, path
("LFD") In the critical path method, the latest possible date that an activity may be complete d without delay ing a specified milestone (usually the project finish date). [D00904] PMK96
The latest date a project task or activity can be completed without delaying the entire project.
In the critical path method, the latest possible date that an activity may be completed without delaying a specified milestone (usually the project finish date). (PMI)